Crude Plant Debottleneck Project

Client

Husky

Schedule

1994 -1994

Industry

Energy

The purpose of this study was to develop a preliminary cost estimate to debottleneck the existing Husky crude unit from 63,000 BPSD to 80,000 BPSD by adding a vacuum tower.  The aim was to increase the total feed to the unit while maintaining the same feed rate to H-Oil hydroprocessing units from the bottom of the vacuum tower.

Services Provided

  • Engineering